Construction Updates

Schedule, notices and a direct line to the project team.

Where we are now
Preparing to start site work
Next: site mobilization in December
Aerial view of the Rockwood Parc site, highlighted in green, between Larz Anderson Park, the Greek Orthodox Metropolis of Boston and Jamaica Pond
The site, shown in greenView full size

Schedule

Target dates. They can shift with weather, permits and inspections. Changes will be posted here.

  1. December 2026

    Site mobilization

    Setting up the site and opening access.

    • Mobilize the site: fencing, erosion controls and tree protection
    • Selective clearing
    • Avon Street access road
    Upcoming
  2. January 2027

    Site grading

    Shaping the site ahead of blasting.

    • Rough grade the internal way
    • Prepare building locations for selective blasting
    • Pre-blast condition surveys of nearby buildings
    Upcoming
  3. February 1, 20274–6 weeks

    Drilling & blasting

    Controlled blasting to remove ledge. See the blasting section below.

    • About 25,000 cubic yards of rock to remove
    • Licensed blaster, vibration monitoring and a warning before every blast
    • Weekday daytime hours only
    Upcoming
  4. March – April 2027

    Rock crushing, grading & utilities

    Turning blasted rock into fill and building the site's infrastructure.

    • Rock crushed and screened on site, then reused as fill and road base
    • New water, sewer and drainage lines
    • Building excavation and foundations for Phase 1
    Upcoming
  5. May 1, 2027

    Phase 1 construction begins

    Framing and building of the first residences. Activity becomes most visible from this point.

    Upcoming
  6. To be posted

    Later phases & landscaping

    Remaining residences, paving, planting and restoration.

    Upcoming

Last reviewed November 25, 2026.

Rock blasting

The site sits on ledge, so rock has to be removed with controlled blasting before foundations can go in.

Feb 1, 2027
Expected to last 4–6 weeks
  1. Licensed blasting contractorWork is done under an approved blast plan and Massachusetts blasting rules, with a new design for each blast area.
  2. Pre-blast surveysWe'll photograph and document neighboring buildings before blasting starts. Abutters can request a survey of their home.
  3. Vibration monitoringEvery blast is monitored at nearby locations and logged. If readings are unusual, work stops.
  4. Warning before every blastAudible warning signals sound and the blast area is cleared and secured. Blast mats are used where needed.
  5. Daytime onlyDrilling and blasting happen only on weekdays, within approved construction hours. There is no blasting at night or on weekends.
  6. Rock reused on siteBlasted rock is crushed on site and reused as fill, which means far fewer trucks on neighborhood streets.

Around the site

HoursWeekdays, 7 a.m.–6 p.m. No routine weekend work.
TrucksUse the designated site access only. Streets swept clean.
DustWater spray on haul roads, stockpiles and the rock crusher.
TreesProtected trees are fenced before any clearing begins.

Updates

  1. Construction page launched

    Schedule and notices will be posted here.

  2. Blasting dates set

    Controlled blasting is planned to begin February 1, 2027, for about 4–6 weeks.

Questions or concerns?

Messages go straight to the development team.

For an urgent site issue, put "URGENT" in the subject line.